|
Change Orders: Causes
and Preemption
By Richard Fanelli, AIA, CFM, IFMA Fellow
Recently Fanelli McClain polled a group of general contractors
specializing in commercial projects. Seventeen responded to the
survey. Based on their thoughts, it was determined the most common
causes of change orders were as follows:
- 58% caused by client-initiated changes
- 17% due to errors and/or omissions in the drawings and/or
specifications
- 17% due to field conditions
- 9% due to any number of
other situations, including permit or code compliance issues,
differences between bid drawings vs. the final construction drawings,
and substitutions of materials due to lead time and value engineering.
Change orders are usually costly and can create delays in the
construction completion schedule. Many can be avoided by focusing
the entire project team on a singular goal: the client’s
satisfaction. Secondly, it is important to establish quality control
procedures early in the process. Here are some best practices that can be implemented:
- Get the end users to sign off on space plans,
finish selections and construction documents. Keep these on file,
in case you have to refer to them at a later date. Inform the
end-user that any changes or increases to the scope of work will
be charged back to them and will affect the completion date.
This includes A&E fees as well as construction costs. They
may think twice before suggesting any changes.
Errors and omissions in A&E drawings can
be drastically reduced by increasing the communication between
the architectural and the engineering teams. Insist that engineers
get involved early in the design process so the engineers can
have input in the space design. This can be done with a simple
project kickoff meeting among the facility manager, architect
and engineers. This should occur after the programming is completed
and before the space planning is finalized. Just this step alone
could save on construction costs—ensuring the proper floor
space is allocated for electrical and mechanical equipment. The
A&E
team should then have a follow-up meeting after the engineering
design intent package is completed by the architects. The engineering
package includes the power and communications plan, the lighting
plan, the equipment plan and the plan indicating the placement
of slab to slab partitions.
Another second A&E coordination
meeting is advisable when the drawings are at 80 to 90 percent
complete. The A&E team should “walk” the facility
manager and all of the team through the drawings. It helps
to distribute the drawings a day or two before the review meeting,
so that a list of questions and concerns can be developed.
- Most common field condition problems, or
hidden conditions, are hard to avoid without exploratory demolition.
The majority of facility managers do not want to disrupt the
space prior to the overall demo phase. As-built drawings provided
by the building owner or building engineer are rarely accurate
and reflect the actual “as-Built” conditions. To
properly verify the existing conditions you must do the following:
- Field-verify overall measurements and measurements between
fixed elements. Check above ceiling tiles to view obstructions that may prevent
achieving the required clearances.
- If the building’s original base building construction
documents are available, review them carefully. It is amazing
what field conditions easily can be uncovered with minimal research.
- Permit and code issues can be avoided, in general,
by conducting a preliminary code review of the space plan by
conferring with the fire marshal. Prepare a meeting report documenting
the resolution to the issues so that you can refer to it, should
the need arise. Of course, the field inspector will always have
the last word on how the A&E drawings address the code requirements.
Take a hard look at any issues that typically come up in the
plan review process such as ADA compliance, egress issues and
life safety upgrades.
- Beware of general contractor’s substitution of
materials and equipment. Make sure that the alternate selected
is of equal quality. If it is inferior to the original specification,
and you are willing accept it, make certain that you receive a
fair credit. Value engineering doesn’t necessarily have to
mean “job cheapening”.
Richard Fanelli, AIA, CFM, IFMA Fellow, is a
principal with Fanelli McClain Design Studios, Inc.,
Fairfax, VA. On the Web: www.fmstudios.com
|