|
Encasement Bests Removal for Asbestos and Mold
By Beth Leibson Hawkins
Being North America’s largest asbestos encasement installation, at 4.2 million sq.ft., is a dubious honor. Especially when it involves four mechanical floors plus a two-level mechanical penthouse, amounting to 1.25 million sq.ft. of space.
“We have a lot of structural steel, all coated with between 5% and 10% crysotile asbestos fireproofing,” says
Bart DeVries, project manager of Capital Development for Ontario-based
Hamilton Health Sciences, a family of five hospitals and a cancer
center. The building has full mechanical floors, known as interstitial
spaces, located between each occupied floor. All mechanical and
electrical services for the building are routed through these spaces
into the occupied floors.
Every time Hamilton Health Sciences wanted to undertake a simple
project in the mechanical spaces, say making a minor adjustment
to the fire alarm, all facilities management employees had to don
protective suits and respirators and decontaminate themselves and
all tools and materials before leaving the mechanical spaces. The
process and downtime almost doubled the trouble and expense of
routine maintenance, even changing a light bulb, DeVries explains.
But this situation could not continue. Hamilton Health Sciences
faced two major problems: First, the asbestos was falling off the
structural steel, creating a health hazard for facilities management
and other employees, and decreasing the fireproofing protection.
Second, the center planned to undertake a major renovation in the
interstitial spaces, a three-year sprinkler installation and fire
alarm system update. DeVries estimated that the presence of asbestos
would increase labor costs by approximately 30%, bringing a $15
million dollar project up to between $18 million to $20 million.
It was time to take action.
Generally, there are three approaches to dealing with asbestos:
removal, encapsulation, and encasement.
Hamilton Health looked into the cost of removing all asbestos.
But it carried an estimated $150 million price tag, which was prohibitive,
particularly for a government-run university and hospital. In addition,
the structural steel would have to be re-fireproofed, with no guarantee
that the replacement materials were any safer. And encapsulants
would add weight to the fireproofing, which might cause problems.
So Hamilton Health decided on encasement.
Asbestos encasement—as well as encasement of lead-based
paint—is a two-part process. First, contractors spray
on a primer, which coats the surface and prepares it for the
sealer, which effectively shrink-wraps the entire surface and
keeps the asbestos from flaking off or otherwise affecting occupants.
However, neither coating affects the flame-retardant qualities
of the original asbestos coating, which is important as asbestos
remains the single most effective flame retardant commercially
available.
The health center selected products from Environmental Coatings,
Inc.(ECI), based in Montclair, New Jersey . The products generate
virtually no airborne fibers, have no volatile chemical organisms
(VOCs), and are completely harmless. “One of our consultants
routinely sprays his salad with our product, then eats it for lunch,” says
Joe Cusenza, president of ECI. Products are guaranteed for up to
ten years but are expected to last indefinitely within temperature
or humidity-controlled environments or indoors.
“We started the encasement program in 2003,” says
DeVries, “and we figure we have probably already paid the
$8 million investment, just by being able to access our mechanical
floors more easily.”
Works for mold, too
This approach also works on mold, though that is a somewhat more
complex process, according to Charles Schwartz, owner and principal
consultant at Scarsdale, New York-based Environmental Assessment
and Solutions Associates.
“Mold rarely appears in a vacuum,” says Schwartz.
“Humidity plus dust produces mold,” says Bruce Jazwinski,
manager of Mamaroneck, New York-based Nu-Air Solutions. “Dust
is a food source for mold, which can irritate the throat, eyes,
and breathing, particularly for people with asthma.”
To solve a mold problem, the company must understand the cause
of the mold and address that—be it a leaky pipe, façade,
or roof, a need for back-up power, or some other cause.
Next, the contractor must remove all molds from the affected
area. Mold is a living material, so it will continue to grow if
not removed. Removing mold also involves removing all water-damaged,
rotted, and mold-ridden building materials, furniture, sheetrock
walls and ceiling, and other materials. The process often involves
multiple applications of HEPA (High Efficiency Particulate Air)
filters.
Biocides are generally not recommended for this process, says
Schwartz, as they are almost as dangerous to humans as the mold
they treat. In some circumstances though, such as sewage spillage
or backup, they actually are the most appropriate solution.
Once the mold is removed, says Schwartz, encasement with safe
products can keep it from growing back, making the process a very
useful investment of time and money for most facilities.
|